The correct operation method of Raymond Mill

Raymond mill and Raymond grinder  or pendulum pulverizer, the main components of the equipment use high quality casting and molding manufacture, from sophisticated manufacturing process to strict production process, to ensure the durability of the Raymond mill. Raymond pulverizer open shutdown sequence to be in accordance with the process, in preparation for the work, installation and debugging work to do a good job in all aspects of the data analysis and spare parts supply.

Ready to work

1, Raymond mill site operation has not been installed, should be properly kept, the exposed surface shall be coated with antirust oil, and to avoid the sun and rain, to prevent the body rust water, to establish a maintenance system.

2, workshop and foundation should be according to Raymond mill foundation drawing size shall be of sufficient height and the installation of the installation position, Raymond mill foundation should adopt high standard cement and shall be buried reinforced base pouring, and pre buried threading pipe or cable trench.After the cement foundation is poured well, must have 15 days of the maintenance period.

3, should be equipped with 2 ~ 3 tons lifting tool for installation, repair by Raymond mill.

4, Raymond mill from the factory to use for longer than 6 months were, the host center shaft system, transmission device, grinding roller device, analysis of oil tank should be clean and check and cleaning after the inspection is completed with the components join enough oil.

Installation work
1, the first transmission device base hanging into the pit filled, pay attention to the control of a certain height, and level of instrument correction at the upper end of the plane, at the same time, the driving device is arranged in the plane with bolt.

2, Raymond Mill installation. Before installation should be in contact of the lower end of the base plane and the cement foundation and anchor bolt connection between pad of rubber shock pad, and then use the box shape of the level of instrument calibration plane of the base, school punctuality for cross line four point, also is two and a half couplings, the different shaft should be less than 0.20 mm.

3, pipeline installation position and height should be installed according to the general plan, shall not be arbitrarily changed and heightening, the pipe joints should be sealed, after fastening shall not be leakage phenomenon. Electrical equipment should be accurate and reliable, and should be carried out after the completion of the installation of the test machine.